Tuesday, October 27, 2009

Construction Update #67




Trackwork continued at a feverish pace, helped along by better weather. Track 46 was completed outside, and connected to the building. Shortly thereafter, track 45 was completed outside and connected to the building. Track 45 was also completed inside. The missing section of track 44 was also built and connected to the building. By the end of the day, tracks 44, 45 & 46 were completed. Due to the weather delays, tracks 41-43 have yet to be connected, but the missing sections on each track are 92 feet long - this represents another day of work to finish. Concurrently with the trackwork, the #46 switch was lifted and blocked, and the floor forms on the north wall were completed. If the weather co-operates, the concrete will be poured this coming week, and the trackwork will be completed shortly thereafter.

1 comment:

Jim Sorensen said...

Thanks for updating the blog - gives me some pictures to look at.
Seems like you are really progressing well. I hope the 'big pour' went well on Wednesday.