Sunday, October 11, 2009

Construction Update #62

The forms for the east slab are about half done, and the track drains are also about half complete. The floor slab forms were stripped from the south wall today, and are ready for re-use on the north wall. The East slab will be poured in sections over the next 2 weeks, and it is hoped to pour the north slab at the end of next week.

Funds for track material are still needed. Please contribute if you can.

No comments: