Tuesday, October 27, 2009
Construction Update #64
Concrete pour #3 was completed on Wednesday October 21. The east pad was poured between the rails on tracks 41-44 and 46. Concurrent with the pour, the drain was installed on track 46, and the catchbasin frames and risers were installed on Tracks 41-44 & 46. Unfortunately, the pour was hindered by the weather - the forecasted "Late afternoon showers" actually arrived as a monsoon as the concrete was being placed. As a result, some reqork will be required on tracks 41 & 42.