Thursday, October 23, 2008

Construction Update #36


Installation of the cladding is now complete. The west wall (Line 9) was closed in yesterday as planned. Remaining, is installation of closures and trim at the North-West corner and trim around the door into the archives. There is also still one mandoor missing on Line K for which the erector is waiting for the frame to come in.