The majority of the soffit trim and steel closures were installed on Line K. Installation of the cladding on Line 9 continued. I was advised that the cladding will be complete by Wednesday - we'll see. The delivery of the firewall material has been delayed until November 14.
Wednesday, October 22, 2008