Tuesday, October 21, 2008

Construction Update #34


After a few days off, the boys were back at it again yesterday. The soffit closures were installed on Line A, as was the mandoor at the east end of Barn 3. The mandoor was also installed on Line 1 (East End). Installation of the soffitt trim & closures on Line K is underway, and they appear to be saving the installation of the cladding on Line 9 next to the boxcar for last. Please excuse the less frequent updates, but progress is going to be hit & miss for the next couple of weeks until installation of the fire wall can commence.