Construction Update #54
Wednesday saw a lot of progress and a couple of milestones. The ballast inside the barn(Which was placed last fall) was fine graded by a contracted dozer and operator. It is now perfectly level, and ready for track. The entire area north of the building was graded, trimmed, and 225 tons of grusher run was placed and graded. The ballast apron east of the building was also fine graded in preparation for track work. Installation of the forms on the south side of the building continued and they should be complete by the end of the week. An inordinate amount of work was accomplished in a single day by a few people, and the project is moving ahead on plan and on schedule.