Monday, September 14, 2009
Construction Update #53
Momentum is building. Over the weekend, the stockpiled ballast was moved out of the way of track construction, and the subdrainage system was installed. The form material is all on site, and installation of the south floor form will start tomorrow. The ties have been moved into a central stockpile, and they will be sorted and stripped later this week. The contract dozer will be on site Wednesday to fine grade the preballast and the building envelope, and by the end of this week the area will be unrecognizable.
Funds for track materials are still needed - please contribute if you can.