Saturday, September 12, 2009
Construction Update #52
Cleanup of the site is nearly complete. A subdrainage system is being installed, and the stockpiled ballast is being relocated to make room for track construction. The material for the floor forms is on site and installation will commence next week. A contractor has been hired to fine grade the pre-ballast inside the barn as well as the building envelope next week. Track construction will commence on September 25, and will be complete by the end of October. Funds for track materials are still needed - please contribute if you can.