The footings on Lines F and K were formed and poured. The piers on Lines A and C were stripped, and will be set on Lines F and K today. The plan is to pour the balance of the piers today, strip on Saturday and backfill all weekend. Erection of the superstructure for the south half of the building is scheduled to start next Monday.
Thursday, September 4, 2008