Installation of the exterior cladding & ceramic firestop on line A is complete except for trimming. Attention will now turn to installing the roof sheeting on the south half of the building. This will facilitate installation of the fire rates interior wall during inclement weather if required.
We plan to apply for a grant to install track doors, install concrete walkways around the perimeter of the building (on the inside), and purchase ties to construct the 1080 feet of track inside the barn this coming winter. I have finished assembling all the various quotations, and we'll keep our fingers crossed that the application is successful.
No comments:
Post a Comment