Monday, September 29, 2008

Construction Update #21


Work on the roof continues to progress well. About 40% of the roof on the north half of the building has now been installed. Between installing the balance of the sheeting and the ridge panel, there are about two days work to be done to complete the roof. So far, the weather has been excellent throughout construction, but with fall slowly arriving, rain days will become more frequent. The plan is to continue with cladding and framing as the weather permits, and install the firewall on rain days. Donations are still coming in, but your continued support is still needed. We submitted our grant application for the walkway slabs, end doors and ties today. We expect to hear whether our application was successful or not by mid-December.