The south half of the roof is now virtually complete. The concrete for the missing door piers was poured yesterday, and the concrete work is now complete. New anchor bolts were installed on line K to account for a layout error, and the building is now fully secured to the foundations. With the piers complete, the endwall framing on lines 1 (east wall) and K (north wall) can now be completed.