Friday, August 8, 2008

Pre-Construction Update #3

Things are finally rolling along! I received word yesterday that the Building Permit is approved and ready to pick-up. Next week, we'll finalize the development charges with the Town, and get the permit issued. Foundation layout will take place the week of August 18th, and the foundations will be excavated between August 22 and 24. I expect that the foundations will be completed by the end of the first week of September, and erection of the red iron will commence shortly thereafter. Donations continue to be received, and we are getting closer and closer to our goal. Please keep those contributions coming!

No comments: