Thursday, August 28, 2008

Construction Update #2

Work on the foundations is progressing well. The Building inspector was on site on Tuesday and approved the excavations. Wooden forms and reinforcing steel mats were installed yesterday on Lines A and C (South wall and South row of interior piers) and the concrete is being poured today. The piers on Line A and C will be poured tomorrow, and the process will repeat early next week on Line F and K (North row of interior piers, and North wall). The excavations will be backfilled the weekend of September 6 & 7, and erection of the superstructure will commence on September 8th.

No comments: