Thursday, November 20, 2008

Construction Update #40


Work by the contractor resumed on November 15, when the two small roll-up doors were installed. The Roxul was delivered on Monday November 17, and installation was 90% complete by the end of Tuesday. Installation of the liner panel commenced yesterday, and the balance of the firewall and installation of the final mandoor is expected to be complete by the end of the week. There are a few deficiencies to correct, but the contract will be substantially complete in the next few days.

No comments: