Monday, April 4, 2011
Sir Adam Beck Centre upgrades complete!
It has been a busy winter, but a number of upgrades in the SAB building are now complete. A new centre walkway was installed, along with additional lighting. A viewing platform has been constructed, and offers a unique vantage point for photos. A number of cars have been rearranged to better display them, and there are new vehicles on display. The rear wall of the building waqs partially removed to integrate it into the existing display building allowing for a much broader viewing experience. The rapid transit cars are in the process of being readied for access by visitors - Stairs, platforms & lighting has been installed. Once we get power to the vehicles interior lights, this area will be opened to the public as well. Come out and see all the improvements!
Sunday, November 7, 2010
Sir Adam Beck Centre Open!
The building officially opened on September 11, 2010. While a lot of work remains to complete all of the little details, the building is open to the public, and fulfilling its intended function. With constrction complete, updates will be infrequent, but I'd like to encourage you to come out and see the building for yourself.
Thursday, September 9, 2010
Official Opening
Join us this Saturday, Sept. 11 at 1:00 p.m. for the official opening of the Sir Adam Beck Centre!
Master of Ceremonies:
A slideshow of the construction, displays and light refreshments will also be available. Don't miss out!
Master of Ceremonies:
- Judi Cohen - Vice-President - Transportation, SNC Lavalin
- Mayor Gordon Krantz, Mayor of the Town of Milton
- Michael Roschlau, President and Chief Executive Officer of the Canadian Urban Transit Association
- Jan Mowbray, Milton Ward 3 Councillor
- Tom Twigge-Molecey, General Manager of the Halton County Radial Railway
- Jim Borland, President of the Ontario Electric Railway Historical Association
A slideshow of the construction, displays and light refreshments will also be available. Don't miss out!
Tuesday, November 10, 2009
Construction Update #75
All in all it was a tremendous weekend, and the current phase of the project is substantially complete, 2 weeks ahead of the scheduled completion date published in the August 8 workplan. With the concrete work and track construction complete, we can concentrate on minor deficiencies and cleanup. My sincerest thanks to everyone who has assisted so far. While a lot of work remains to ballast, lift and tamp the yard, and complete the electrical work and parts shelving in the building, we have accomplished the goal of getting the building ready for cars this fall.
Construction Update #74
The final concrete pour took place Saturday morning. The slabs adjacent to track 45 were poured, along with the slabs in front of the doors on the north side of the building. Unfortunately, the load of concrete was about half a meter short of finishing the last door slab so it will be completed with redi-mix. With the concrete pouring out of the way, attention turned to track construction. Track 45's north rail was spiked inside the building, and ties were laid out for tracks 41, 42 and 43 outside. The line and gauge rail were installed on track 42 and 43 before we ran out of light. The line rail was also set on track 41 in preparation for Sunday. Concurrent with the above, the track 46 and #7 switches had the ballast levelled off, and they were tapmed using the air tampers and a rented compressor.
Construction Update #73
Subscribe to:
Posts (Atom)