All in all it was a tremendous weekend, and the current phase of the project is substantially complete, 2 weeks ahead of the scheduled completion date published in the August 8 workplan. With the concrete work and track construction complete, we can concentrate on minor deficiencies and cleanup. My sincerest thanks to everyone who has assisted so far. While a lot of work remains to ballast, lift and tamp the yard, and complete the electrical work and parts shelving in the building, we have accomplished the goal of getting the building ready for cars this fall.
Showing posts with label 2009. Show all posts
Showing posts with label 2009. Show all posts
Tuesday, November 10, 2009
Construction Update #75
Construction Update #74
The final concrete pour took place Saturday morning. The slabs adjacent to track 45 were poured, along with the slabs in front of the doors on the north side of the building. Unfortunately, the load of concrete was about half a meter short of finishing the last door slab so it will be completed with redi-mix. With the concrete pouring out of the way, attention turned to track construction. Track 45's north rail was spiked inside the building, and ties were laid out for tracks 41, 42 and 43 outside. The line and gauge rail were installed on track 42 and 43 before we ran out of light. The line rail was also set on track 41 in preparation for Sunday. Concurrent with the above, the track 46 and #7 switches had the ballast levelled off, and they were tapmed using the air tampers and a rented compressor.
Construction Update #73
Construction Update #72
Thursday was another productive day. The curb form was completed first thing in the morning, as was the catchbasin frame for Track 45. The first concrete truck arrived at 0900, and the curb was poured. The second truck arrived at 1030, and the ramp into the parts area was poured, along with the pad between the rails on Track 45. Once the concrete set up, all of the curb forms were stripped to allow for finishing. As well as being a nice cosmetic detail, the curb performs an important stormwater management function - It retains the cobbles which break up the run-off from the roof, and directs the runoff into the drain pipe along the wall, which in turn carries the stormwater away.
Subscribe to:
Posts (Atom)